Construction Timeline
SUMMER 2017
- Periodicals & Electronic Resource Services moves from 6th floor to 4th floor
- Art Resource Lab moves from 5th floor to 6th floor
- 50 Computer workstations move to the 6th floor
Fall 2017
- Periodicals and Resource Services reopens
- E404 Opens as a Forecast/Library Instruction Room
- 6th floor space reopens as open work space with a maker space, computing resources, art resources
Completed Projects
SPRING 2017
- SPARC reopens in renovated space
- AMS unit moves into renovated space
SPRING 2016
Demolition and construction begin in 4th & 6th floor construction sites
25 student computer workstations and 6 scanners available on the 4th floor public
space during library hours
SPARC resumes operations
WINTER 2016
- 4th floor library services are temporarily closes
- Elevator access to the fourth floor is suspended until project completion
- Special Collections Resources and Offices move to temporary space